INTERMITTENT PROTOTYPE KILN: CONSTRUCTION PHASE FINISHED

The prototype of the Economick kiln was assembled in its various parts at SE.TE.C. srl premises, in Civita Castellana (VT).

The kiln construction included the following main stages:
- carpentry assembly and painting;
- assembly of walls insulating layers and of combustion chamber refractories
- burners arrangement and gas pipes construction
- assembly of the air / fume heat exchange system, with the relative fans
- kiln door assembly.

ECONOMICK kiln is being transported and installed within Kerasan srl ceramics working site (partner of the project) for firing tests on ceramic sanitary products.

For other information you can visit the site www.economick.eu.